 - Ten West Link 2022

Rockfall barriers protecting the transmission line towers.

 - Ten West Link 2022

Lateral view of the rockfall barrier

 

Systems

 

System length

- 230 m

 

Year of installation

2022

Situation

The Ten West Link project is a new power project from Southern Arizona & California. The project goes across the Eagletail Mountains & Wildreness, where transmission line towers will be built.

Description

Geobrugg was tasked with providing ten GBE-100A-R rockfall barriers to protect ten transmission line towers that will be built. The barriers are three meters high with a total length of 230 meters.

These barriers will protect personnel, roadway and future transmission lines. This particular transmission line will span 125 miles connecting Arizona and California, improving transmission system efficiency and reliability.

Thank you Adams Contracting for the pictures. 

Country/Region

アメリカ合衆国

Contractor

Protected object

道路, インフラ

Corrosion protection

亜鉛めっき

Your local contact

René Müller
   

René Müller

Country Manager Western Switzerland

自然災害防護
Hydraulic Engineering
鉱山/トンネル
モニタリングサービス
Geobrugg AG,Industriestrasse 21,5200 Brugg / スイス Country Manager Western Switzerland

E-Mail

Olivia Sartorius
   

Olivia Sartorius

Project Manager Sales Eastern and Central Switzerland

自然災害防護
Hydraulic Engineering
鉱山/トンネル
モニタリングサービス
Geobrugg AG Project Manager Sales Eastern and Central Switzerland

E-Mail

Isacco Toffoletto
   

Isacco Toffoletto

Country Manager Southern Switzerland

自然災害防護
Hydraulic Engineering
鉱山/トンネル
モニタリングサービス
Geobrugg AG Ticino,Via Brusada 5,6933 Muzzano / スイス Country Manager Southern Switzerland

E-Mail