Ligne Montréjeau-Luchon - Reprofilage du tunnel Cap du Mail

터널, 광산 - Ligne Montréjeau-Luchon - Reprofilage du tunnel Cap du Mail 2024

The renovated tunnel, secured with a system of rock bolts and mesh.

터널, 광산 - Ligne Montréjeau-Luchon - Reprofilage du tunnel Cap du Mail 2024

Tunnel re-profiling using a tunnel saw

터널, 광산 - Ligne Montréjeau-Luchon - Reprofilage du tunnel Cap du Mail 2024

Additional local re-profiling using a hydraulic rock breaker

터널, 광산 - Ligne Montréjeau-Luchon - Reprofilage du tunnel Cap du Mail 2024

Installation of MINAX G80/3 mesh, protecting against falling debris

 
 

설치 년도

2024

Situation

As part of the rehabilitation work on the Montréjeau-Luchon railroad, the Cap du Mail tunnel needed to be reprofiled to allow the passage of the new trains, which are wider than the old ones.

Description

The new clearance profile for this 70-meter tunnel was achieved by cutting back the tunnel by an average of 20 cm. Subsequently, a safety system for future rail traffic was installed using a combination of rock bolts and MINAX mesh.

Country/Region

프랑스

Customer

La Région Occitanie

Engineering

Société Alpine de Géotechnique

Contractor

NGE Fondations

Subcontractor

Alsacienne de minage et démolition

Protected object

Railway

Your local contact

René Müller
   

René Müller

Country Manager Western Switzerland

자연 재해
수리학
광산 / 터널
모니터링
Geobrugg AG,Industriestrasse 21,5200 Brugg / 스위스 Country Manager Western Switzerland

이메일

Olivia Sartorius
   

Olivia Sartorius

Project Manager Sales Eastern and Central Switzerland

자연 재해
수리학
광산 / 터널
모니터링
Geobrugg AG Project Manager Sales Eastern and Central Switzerland

이메일

Isacco Toffoletto
   

Isacco Toffoletto

Country Manager Southern Switzerland

자연 재해
수리학
광산 / 터널
모니터링
Geobrugg AG Ticino,Via Brusada 5,6933 Muzzano / 스위스 Country Manager Southern Switzerland

이메일