Швейцария
Швейцария

myGeobrugg

ANA Chosica - 22 barriers for nine valleys

Селевые потоки и микросели - ANA Chosica - 22 barriers for nine valleys 2016

Attaching the net to the cable

Селевые потоки и микросели - ANA Chosica - 22 barriers for nine valleys 2016

Installing abrasion protection (in front a brake ring) ...

Селевые потоки и микросели - ANA Chosica - 22 barriers for nine valleys 2016

... which protects the rope when the net is filled and there is an overflow.

Селевые потоки и микросели - ANA Chosica - 22 barriers for nine valleys 2016

Final check executed by the installation team.

Селевые потоки и микросели - ANA Chosica - 22 barriers for nine valleys 2016

The lower barrier with a top width of 60 m. Project specific UX-barrier line-up with 5 posts.

Селевые потоки и микросели - ANA Chosica - 22 barriers for nine valleys 2016

Serial alignment acoording to the multilevel approach (planned with DEBFLOW software).

Селевые потоки и микросели - ANA Chosica - 22 barriers for nine valleys 2016

Protection system and protected object.

Селевые потоки и микросели - ANA Chosica - 22 barriers for nine valleys 2016

Site visit with representatives of the client.

Селевые потоки и микросели - ANA Chosica - 22 barriers for nine valleys 2016

The proud team aside of its record installation in record time - full satisfaction.

Селевые потоки и микросели - ANA Chosica - 22 barriers for nine valleys 2016

2017, one year later: Approximately 7000 m³ debris were stopped in this barrier.

Селевые потоки и микросели - ANA Chosica - 22 barriers for nine valleys 2016

2017, one year later: The second barrier level contains approximately 3000 m³ debris.

Селевые потоки и микросели - ANA Chosica - 22 barriers for nine valleys 2016

2017, one year later: View uphill from 2nd level to first level of the filled barriers.

Селевые потоки и микросели - ANA Chosica - 22 barriers for nine valleys 2016

2017, one year later: The city is close to the activated barriers.

Селевые потоки и микросели - ANA Chosica - 22 barriers for nine valleys 2016

2017, one year later: The fourth level of the barriers is nearly not affected and still fully functional.

Селевые потоки и микросели - ANA Chosica - 22 barriers for nine valleys 2016

September 2018: Repair works for the anchors

 

Системы:

 

Длина системы:

6 m - 60 m

 

Год установки:

2016

Ситуация:

In the area east of Lima, Peru, annually recurring rains due to the El Niño phenomenon caused mudslides and landslides in the past. At the end of February 2016, Geobrugg installed 22 debris flow barriers that today protect people and infrastructure in the nine valleys of the Chosica Region.

Описание:

22 barriers were installed between mid-November 2015 and end of February 2016. Noteworthy are the means of transportation: By air from Switzerland to Lima and by muscle power over the final kilometers. The lightweight of the systems was advantageous for both types of transport.

Local authorities show details of the largest installation of this kind of Latin America in a film (in Spanish).

March 2017

A year after the installation of 22 debris flow barriers in Chosica El Niño Costero has struck again, with the worst storms of the past 30 years in the north of Peru. Causing heavy rains, floods, and landslides, which have caused in fatalities and damage to properties.

The 22 barriers have functioned reliably. One of the images shows a 55 meters stretch as one of the 4 levels of the barrier system. Two of these barriers are filled to 95 percent capacity, which is a volume of 10,000 m³. The multilevel design allows an increased retention volume, meaning that there is still capacity in the downstream barriers. The most important thing is that the residential area has not been damaged and there have been no deaths or injuries.

September 2018
Desnivel Perú S.A.C, Spanish-Swiss parent company, concluded the restoration and replacement works of affected elements after the Niño Costero period that shook the Peruvian coast in 2017.

The works consisted of two stages: The removal of material accumulated after the rainy season. And the replacement and restoration of the elements damaged by the debris flow and by robberies.

The following pictures illustrate 2016, 2017 and 2018.

Страна/Регион:

Перу

Клиент:

ANA Chosica

Проектировщик:

TDM S.A.

Подрядчик:

TDM S.A.

Защищаемый объект:

Дорога, Строительство

Защита от коррозии:

GEOBRUGG SUPERCOATING

Представитель в Вашем регионе

René Müller
   

René Müller

Country Manager Western Switzerland

Инженерная защита
Гидротехника
Горнодобывающая промышленность / Туннели
Monitoring
Геобругг АГ,Industriestrasse 21,5200 Brugg / Швейцария Country Manager Western Switzerland

Электронная почта

Olivia Sartorius
   

Olivia Sartorius

Project Manager Sales Eastern and Central Switzerland

Инженерная защита
Гидротехника
Горнодобывающая промышленность / Туннели
Monitoring
Геобругг АГ Project Manager Sales Eastern and Central Switzerland

Электронная почта

Isacco Toffoletto
   

Isacco Toffoletto

Country Manager Southern Switzerland

Инженерная защита
Гидротехника
Горнодобывающая промышленность / Туннели
Monitoring
Geobrugg AG Ticino,Via Brusada 5,6933 Muzzano / Швейцария Country Manager Southern Switzerland

Электронная почта